Jinmingyu Construction·Progress

  • Categories:Special Column
  • Author:
  • Origin:
  • Time of issue:2020-09-29 10:34
  • Views:

(Summary description)The ground beam formwork support of the apartment building is 1/2 completed;2.The installation of the steel column and steel beam of the scientific

Jinmingyu Construction·Progress

(Summary description)The ground beam formwork support of the apartment building is 1/2 completed;2.The installation of the steel column and steel beam of the scientific

  • Categories:Special Column
  • Author:
  • Origin:
  • Time of issue:2020-09-29 10:34
  • Views:
Information

  Technology company:
  1.The ground beam formwork support of the apartment building is 1/2 completed;2.The installation of the steel column and steel beam of the scientific research building is 1/3 completed;3.The foundation wire of the light steel workshop is installed;4.The autoclave foundation of the light board production workshop Excavation is complete.
  2,heavy steel 436 tons,PC720 cubic
  Shuhe Ancient Road:
  The three layers on the east and west sides are doing roof insulation,the three layers on the north side are tied with steel bars,the east and west sides of the first floor are laid bricks,and the east side of the second floor is removed.
  Yubo Garden East District:
  1#,2#building exterior windows are installed with glass completed,exterior wall real stone paint is completed;3#building real stone paint is 70%completed;5#,6#building exterior powder is completed,start internal powder;7#building bricklaying is completed,start exterior Fen;Building 8#and 9#began to be built.
  Jin Ming Yu East District:
  6#,8#,10#building foundation raft steel reinforcement;2#building top template assembly;5#building closure;7#,9#,11#building roof waterproof construction,masonry starts;12#,13#,The masonry construction of building 15#is completed.
  Century Garden:
  15#building foundation backfill,first floor formwork support;16#building negative first floor formwork support;21#building negative first floor roof steel reinforcement completed;22#building first floor top slab pouring completed.
  Century Shangyuan East District:
  2#building construction slope roof;5#building five-story cast-in-place surface completed;7#building six-story shear wall steel reinforcement binding completed;9#building three-story cast-in-place surface laying completed;11#building negative one floor tied slab reinforcement;Building 17#is going to tie the raft slab reinforcement.
  Guan Yuyuan South District:
  3#,7#,11#building negative first floor formwork support;4#building negative second floor formwork support;10#,15#building standard four-story formwork support;16#building standard seven-story formwork support;19#Building slope roof to do waterproofing.
  Weiye Century Plaza
  The five-layer beam slab formwork support of Block A is completed;the four-layer beam slab formwork support of Block B is completed.

News

weiye

Contact Us

 

Tel:0539-6263777

E-mail:sdwyjt@126.com

Address: West End of Zhengda Street, Linshu County, Linyi City, Shandong Province

weiye

Mobile site

weiye

Weiye Public Account

Page Copyright © Weiye group      鲁ICP备16000130号-2   Powered by  www.300.cn