Jinmingyu Construction·Construction Group Progress

  • Categories:Special Column
  • Author:
  • Origin:
  • Time of issue:2020-09-29 10:35
  • Views:

(Summary description)2#building roof machine room roof lashing wall reinforcement;5#building standard four-story concrete pouring completed;7#building standard five-story

Jinmingyu Construction·Construction Group Progress

(Summary description)2#building roof machine room roof lashing wall reinforcement;5#building standard four-story concrete pouring completed;7#building standard five-story

  • Categories:Special Column
  • Author:
  • Origin:
  • Time of issue:2020-09-29 10:35
  • Views:
Information

  East District of Century Shangyuan:
  2#building roof machine room roof lashing wall reinforcement;5#building standard four-story concrete pouring completed;7#building standard five-story slab surface template support completed;9#building standard two-story slab surface template support completed;11#building negative Pouring concrete on the second floor was completed;the negative second floor of Building 13#started to support the formwork.
  Century Shangyuan Phase II:
  7#,9#,11#,12#,16#building bricklaying is in progress;11#building waterproof beam fence finished;15#building 10 floor main formwork;16#building waterproof beam fence finished.
  Jingyu Jiayuan East District:
  20#Building machine room template support;19#building roof waterproof protection layer completed;18#building roof railing completed;17#building roof railing completed;17#building south garage erected.
  Jin Ming Yu East District:
  2#Building four-story column steel reinforcement;5#building six-story wall column steel reinforcement;6#floor cushion pouring;7#building roof waterproof construction;8#building paving raft floor waterproofing membrane;9#building standard roof Waterproof paving,masonry construction;10#floor raft steel bar binding.
  Century Garden:
  Construction of the negative first floor of 15#building is completed;16#building negative two-story wall reinforcement;17#building raft steel reinforcement;18#,19#building foundation clearing;20#building negative two-story formwork support;21#building Formwork support on the first floor;formwork support on the first floor of building 22#.
  Guan Yuyuan South District Phase II:
  3#,7#building negative two-story top slab reinforcement;10#building standard two-story beam slab support;11#building negative two-story beam slab support;15#building two-story beam slab support;16#building fifth floor Beam slab support mold.
  Technology Company
  The second phase of the project:completion of the foundation acceptance of the apartment and scientific research building,preparation for backfilling,and completion of the reinforcement of the plant foundation
  Heavy Steel Workshop:A total of 10 orders have been completed this month,a total of more than 1,500 tons have been produced,and more than 2,000 tons have been shipped.
  PC workshop:A total of 8 orders have been completed this month,a total of 1,600 cubic meters have been produced,and 1,200 cubic meters have been shipped.
  Shuhe Ancient Road
  Reception Center:the construction of the third floor of the main body standard is completed,and the masonry construction of the first floor of the standard
  Tourist reception:A total of 56 outreach training teams were received in April;the scenic spot received a total of 6,000 tourists.
  Preferential activities:From May 1st to 7th,forward the activity link of Shuhe Ancient Road Scenic Area to Moments for free admission for 3 days.For more discount activities,please follow the WeChat public account of Shuhe Ancient Road Scenic Area

News

weiye

Contact Us

 

Tel:0539-6263777

E-mail:sdwyjt@126.com

Address: West End of Zhengda Street, Linshu County, Linyi City, Shandong Province

weiye

Mobile site

weiye

Weiye Public Account

Page Copyright © Weiye group      鲁ICP备16000130号-2   Powered by  www.300.cn